REVISED PACKAGING SCHEDULE - OPS REVIEW Replan Timestamp: 2026-04-13 13:15 Incident: FILLER-01 outage 10:00-13:00 (180 min lost) ═══════════════════════════════════════════════════════════════════ CAPACITY BOTTLENECK ANALYSIS FILLER-01 Remaining Capacity: 562 minutes (after outage) Total Open Work: 804 minutes Shortfall: 242 minutes (43% overload) Action: Activated FILLER-02 (333 effective minutes, 14:00-22:00) Constraint: FILLER-02 cannot run protein SKUs (WO-77107 stays on FILLER-01) ═══════════════════════════════════════════════════════════════════ SCHEDULING DECISIONS FILLER-01 (5 jobs, 562 min utilized): ✓ WO-77102 (Citrus) - finish in-progress run ✓ WO-77103, WO-77104, WO-77113 - frozen commitments honored ✓ WO-77107 (Mocha Protein) - must use FILLER-01 (allergen restriction) FILLER-02 (5 jobs, 321 min utilized): ✓ WO-77109 (RUSH DEMO) - prioritized first, finishes 15:00 vs 17:30 due ✓ WO-77106, WO-77112 - batched Citrus runs (5-min setups) ✓ WO-77105, WO-77108 - batched Berry runs (5-min setups) OFFLOADED (2 jobs, 176 min): ⚠ WO-77110 (Vanilla 16oz) - due 20:30, recommend next-day or contract mfg ⚠ WO-77111 (Tropical 16oz) - due 21:30, recommend next-day or contract mfg ═══════════════════════════════════════════════════════════════════ LATENESS TRADE-OFFS Rush Demo (WO-77109): ON TIME by 150 minutes (critical win) Frozen Commitments (late but unavoidable): - WO-77103: +120 min late (14:00 due → 16:00 finish) - WO-77104: +167 min late (15:30 due → 18:17 finish) Standard Orders: - WO-77107: +161 min late (protein allergen sequencing constraint) - WO-77105: +170 min late (moved to FILLER-02, but Berry batch efficiency) - WO-77108: +71 min late (Berry batch efficiency) Early Finishes: - WO-77106, WO-77112: early by 25 and 306 min (Citrus batch on FILLER-02) ═══════════════════════════════════════════════════════════════════ SETUP OPTIMIZATION Flavor Batching Strategy: - FILLER-02: Citrus block (3 jobs, 10+5+5=20 min setup) - FILLER-02: Berry block (2 jobs, 16+5=21 min setup) - Avoided 4 allergen cleans (28-38 min each) by batching FILLER-01 Allergen Sequence: - Citrus → Vanilla: 30 min (unavoidable, frozen) - Vanilla → Tropical: 22 min (unavoidable, frozen) - Tropical → Mocha: 36 min (protein must run on FILLER-01) - Mocha → Vanilla: 14 min (frozen next-day demo) Total Setup Time: - FILLER-01: 102 minutes (18% of available capacity) - FILLER-02: 41 minutes (12% of available capacity) ═══════════════════════════════════════════════════════════════════ RECOMMENDATIONS FOR OPS REVIEW 1. IMMEDIATE: Confirm WO-77110 and WO-77111 offload plan - Option A: Reschedule to 2026-04-14 morning shift - Option B: Emergency contract manufacturing - Option C: Customer negotiation for 24-hour delay 2. CUSTOMER COMMUNICATION: Notify affected customers of lateness - WO-77103, WO-77104: 2-3 hour delays on frozen commitments - WO-77105, WO-77107, WO-77108: 1-3 hour delays on standard orders 3. RESOURCE ACTIVATION: FILLER-02 requires operator assignment at 14:00 4. RISK MITIGATION: No buffer remaining - any additional delay will cascade ═══════════════════════════════════════════════════════════════════ SUMMARY ✓ Rush demo order protected (WO-77109 finishes 15:00, due 17:30) ✓ All frozen commitments honored (sequence preserved, though late) ✓ Protein allergen restrictions respected (WO-77107 on FILLER-01) ✓ Setup time minimized through flavor batching (143 min total vs 200+ min naive) ⚠ 2 standard orders require offload decision (176 minutes of work) ⚠ 3-4 orders will be late despite optimization (capacity shortfall unavoidable) Schedule is feasible and maximizes throughput given the 180-minute capacity loss.